Facilities Planning Projects

Current Campus Projects:


Project Details:

 

Project: D059HV - Alumni Hall Roof Replacement  

Project Phase: Construction Phase
Design Cost: $60,468
Consultant: LaBella Associates 
Construction Cost: $450,000
Contractor: Jamestown Roofing

Expected Start of Construction: May 2020
Expected Completion of Construction: August 2020

LATEST NEWS: Update current through 07/07/20 -- Construction


Project: 051029 - Rosch Recital Hall Roof Replacement  

Project Phase: Construction Phase
Design Cost: $9,575
Consultant: Foit-Albert Associates  
Construction Cost: $148,520
Contractor: A.W. Farrell & Son

Expected Start of Construction: May 2020
Expected Completion of Construction: August 2020

LATEST NEWS: Update current through 07/07/2020 -- Construction complete 


Project: 051026 - Emergency Lockdown Door Hardware  

Project Phase: DESIGN PHASE
Design Cost: $88,610.85
Consultant: 3 Leafs Hardware Consultants  
Construction Cost: TBD
Contractor: TBD

Expected Start of Construction: June 2020
Expected Completion of Construction: Janurary 2021

LATEST NEWS: Update current through 07/07/20 -- This project is currently in the design phase. 


Project: 051030 - IT Emergency Power & UPS Replacement 

Project Phase: Design  
Design Cost: $95,863
Consultant: P Max Engineers 
Construction Cost: TBD
Contractor: TBD

Expected Start of Construction: May 2020 
Expected Completion of Construction: August 2020 

LATEST NEWS: Update current through 07/07/20 -- This project is currently in the design phase.  


Project: 051028 - Fuel Tank System Replacement   

Project Phase: Design 
Design Cost: $50,025.63
Consultant: LiRo Engineers
Construction Cost: TBD
Contractor: TBD

Expected Start of Construction: May 2020
Expected Completion of Construction: August 2020

LATEST NEWS: Update current through 07/07/20 -- This project is currently in the design phase.  


 Project 051024 - Lanford Rehab

Project Phase: DESIGN
Design Cost:  $197,577.09
Consultant:  Flynn Battaglia Architects 
Construction Cost: To Be Determined
Contractor:  To Be Determined

Expected Start of Construction: May 2020
Expected Completion of Construction:  December 2020

LATEST NEWS: Update current through 07/07/20-- This project is currently in the design phase.  

top


Project 051020 - Replace AHUs & Controls Phase V - Mason Hall

Project Phase:  Construction
Design Cost:  $195,310
Consultant:  Wendel
Construction Cost: $2,348,000
Contractor: MLP Plumbing & Mechanical 

Expected Start of Construction: May 2019
Expected Completion of Construction:  August 2020

LATEST NEWS: Update current through 07/07/20-- This project is currently in the construction phase.

top


Project: 05X267 - Renovate Houghton Hall (SUCF PROJECT

PROJECT 05X267-00 - Houghton Hall 1st and 2nd Floor Fitout
Project Phase: Construction 
Consultant:  Mitchell Giurgola
Contractor:  Savarino Companies 
Expected Completion of Construction: August 2021

LATEST NEWS: Update current through 07/07/2020 -- In Construction

top


Project 051011-00: Rehab Exterior Reed Library (SUCF PROJECT

Project Phase: Construction    
Consultant: Bell & Spina  
Contractor: Savarino Companies 
Expected Completion of Construction: Summer 2021

LATEST NEWS: Update current through 07/07/2020 -- In Construction