Facilities Planning Projects

Current Campus Projects:

  • 051038 - Replace Kirkland Plaza
  • 051040 - Maytum Hall Lower Roof Replacement 
  • 051049 - Upgrade A/C & Humidity Controls - Mason Hall 
  • D059IK - Residence Halls Condition Assessment 
  • D059IE - Gregory Hall Exterior Masonry Repair 
  • 051024 - Lanford Rehab
  • 051037 - Rehab Lanford Phase II - Exterior  
  • 051039 - LoGrasso Hall Upgrade AHU & Ventilation System 
  • State University Construction Fund (SUCF) PROJECTS 

Project Details:


Project: 051038 - Replace Kirkland Plaza

Project Phase: Bid Review 
Design Cost: $196,548.14
Consultant: Bergmann
Construction Cost: TBD
Contractor: TBD

Expected Start of Construction: May 2024
Expected Completion of Construction: September 2024

LATEST NEWS: Update current through 12/04/2023 --- 3 bids received on 12/1/23 - Bid Results 

Notice to Bidders          Current Plan Holders List

top


Project: 051040 - Maytum Hall Lower Roof Replacement 

Project Phase: Bid Review 
Design Cost: $155,202
Consultant: Bell & Spina 
Construction Cost: TBD
Contractor: TBD

Expected Start of Construction: May 2024
Expected Completion of Construction: October 2024

LATEST NEWS: Update current through 11/29/2023 --- 2 Bids were received - Bid Results

Notice to Bidders               Current Plan Holders List


Project 051049 - Upgrade Air Conditioning & Humidity Controls - Mason Hall 

Project Phase: Closeout 
Consultant: Pathfinder Engineers & Architects
Contractor: MLP Plumbing & Mechanical                 Construction Cost: $554,913.00 

Expected Start of Services: May 2023 
Expected Completion of Services: August 2023

LATEST NEWS: Update current through 11/14/2023 -- Construction is complete - In closeout phase. 


Project D059IK - Residence Halls Condition Assessment 

Project Phase: QAQC Phase 
Consultant: Young + Wright Architectural  
Contract Cost: $112,477.00

Expected Start of Services: Fall 2022 
Expected Completion of Services: December 2023

LATEST NEWS: Update current through 11/14/2023 -- The Condition Assessment data was turned over to campus in October 2023.   


Project: D059IE - Gregory Hall Exterior Masonry Repair

Project Phase: Construction Phase   
Design Cost: $107,860
Consultant: Bell & Spina 
Construction Cost: $634,316.50
Contractor: Upstate Restoration of NY 

Expected Start of Construction: May 2023
Expected Completion of Construction: October 2023

LATEST NEWS: Update current through 11/14/2023 -- This project is nearing completion.   


Project 051024 - Lanford Rehab

Project Phase: Punch list / Closeout
Design Cost:  $197,577
Consultant:  Flynn Battaglia Architects 
Construction Cost: $1,105,162.73
Contractor: Peak Construction 

Expected Completion of Construction: June 2023

LATEST NEWS: Update current through 11/14/2023 -- This project is in the closeout phase - Waiting on credit items from contractor.  


Project: 051037 - Rehab Lanford Phase II - Exterior 

Project Phase: Design Manual Phase    
Design Cost: $153,872.70
Consultant: Flynn Battaglia Architects 
Construction Cost: TBD
Contractor: TBD

Expected Start of Construction: TBD
Expected Completion of Construction: TBD 

LATEST NEWS: Update current through 11/14/2023 --- This project is currently in the design manual phase.  

top


Project: 051039 - LoGrasso Hall Upgrade AHU & Ventilation System 

Project Phase: Closeout 
Design Cost: $267,428.11
Consultant: M/E Engineering 
Construction Cost: $2,214,948.00
Contractor: John W. Danforth Company 

Expected Start of Construction: May 2023
Expected Completion of Construction: September 2023

LATEST NEWS: Update current through 11/14/2023 -- Construction is complete - In closeout phase. 

top


Project 051010-00: Rehab Maytum/Reed/McEwen Plaza (SUCF PROJECT

Project Phase: On Hold    
Consultant: Bell & Spina
Contractor: Savarino Companies 
Expected Completion of Construction: Summer 2023

LATEST NEWS: Update current through 11/14/2023 -- Project is on hold due to contractor filing bankruptcy.

top


Project: 051022-00 Renovate Jewett Hall (SUCF PROJECT

Project Phase: Design Manual Phase   
Consultant: Mitchell Giurgola Architects

LATEST NEWS: Update current through 11/14/2023 -- This project is currently in the  design manual phase.

top


Project: 051041 - Clean Energy Master Plan (SUCF PROJECT

Project Phase: Report Review   
Consultant: M/E Engineering 

LATEST NEWS: Update current through 11/14/2023 -- M/E Engineering has submitted their draft master plan report to SUCF and the campus for review. 

top


Project: 051042 - Replace Turf Field & Track (SUCF PROJECT

Project Phase: Design Phase
Consultant: PHZ Architects, PLLC

LATEST NEWS: Update current through 11/14/2023 --Artificial Turf Field (Phase I) - In pre-bid document phase, with construction scheduled for the spring 2024; Track & Field (Phase II) - In Design Manual phase. 

top


Project: 051043 - Replace Emergency Generators (SUCF PROJECT

Project Phase: Construction Contract Phase    
Consultant: Pathfinder Engineers
Contractor: Frey Electric 

LATEST NEWS: Update current through 11/14/2023 -- This project is currently in the construction contract phase with Frey Electric.

top


Project: 051044 - Replace Mechanical Equipment - Rockefeller Arts Center (SUCF PROJECT

Project Phase: Design 
Consultant: M/E Engineering 

LATEST NEWS: Update current through 11/14/2023 -- A design kick-off meeting was held on 10/4/23. 

top


Project: 051045 - Rehab Interior Reed Library - Learning Common (SUCF PROJECT

Project Phase: Concept / Schematic Design Phase   
Consultant: Architectural Resources

LATEST NEWS: Update current through 11/14/2023 -- This project is currently in the concept / schematic design phase.

top


Project: 051047 - Mason Hall Siding (SUCF PROJECT

Project Phase: Out for Bid
Consultant: Holt Architects 

LATEST NEWS: Update current through 11/14/2023 -- No bids were received. 

top


Project: 051048 - Mason Hall Renovations (SUCF PROJECT

Project Phase: Design Phase
Consultant: Architectural Resources 

LATEST NEWS: Update current through 11/14/2023 -- A design kick-off meeting was held on October 17th.

top