Facilities Planning Projects

Current Campus Projects:


Project Details:

Project D059IK - Residence Halls Condition Assessment 

Project Phase: Contract Phase
Consultant: Young + Wright Architectural 

Expected Start of Services: Fall 2022 
Expected Completion of Services: December 2023

LATEST NEWS: Update current through 11/29/2022 -- The campus is currently in the contract phase with the selected consultant, Young + Wright Architectural.   


Project: D059IE - Gregory Hall Exterior Masonry Repair

Project Phase: Contract Phase  
Design Cost: $107,860
Consultant: Bell & Spina 
Construction Cost: $590,000
Contractor: Upstate Restoration of NY 

Expected Start of Construction: May 2023
Expected Completion of Construction: August 2023

LATEST NEWS: Update current through 11/29/2022 --- The construction contract has been submitted for final approval. 

BID RESULTS         


Project 051024 - Lanford Rehab

Project Phase: CONSTRUCTION  
Design Cost:  $197,577.09
Consultant:  Flynn Battaglia Architects 
Construction Cost: $944,000
Contractor: Peak Construction 

Expected Completion of Construction: October 2022

LATEST NEWS: Update current through 11/29/2022 -- This project is in construction. 


Project: 051026 - Emergency Lockdown Door Hardware  

Project Phase: CONSTRUCTION
Design Cost: $88,610.85
Consultant: 3 Leafs Hardware Consultants  
Construction Cost: $475,000
Contractor: Huber Construction 

Expected Completion of Construction: February 2023

LATEST NEWS: Update current through 11/29/2022 -- This project is in construction. 


Project: 051037 - Rehab Lanford Phase II - Exterior 

Project Phase: Design Phase    
Design Cost: $153,872.70
Consultant: Flynn Battaglia Architects 
Construction Cost: TBD
Contractor: TBD

Expected Start of Construction: TBD
Expected Completion of Construction: TBD 

LATEST NEWS: Update current through 11/29/2022 --- This project is currently in design.  

top


Project: 051038 - Replace Kirkland Plaza

Project Phase: Design Phase 
Design Cost: $196,548.14
Consultant: Bergmann
Construction Cost: TBD
Contractor: TBD

Expected Start of Construction: May 2024
Expected Completion of Construction: September 2024

LATEST NEWS: Update current through 11/29/2022 --- This project is currently in design and has been deferred for construction until the Summer 2024, with bidding expected in the Fall 2023. 

top


Project: 051039 - LoGrasso Hall Upgrade AHU & Ventilation System 

Project Phase: Bid Review 
Design Cost: $267,428.11
Consultant: M/E Engineering 
Construction Cost: TBD
Contractor: TBD

Expected Start of Construction: May 2023
Expected Completion of Construction: August 2023

LATEST NEWS: Update current through 11/29/2022 --- Bids were received on 11/29 - Bid results have been posted. 

Bid Results           Current Plan Holders List          

top


Project: 051040 - Maytum Hall Roof Replacement 

Project Phase: Design Phase 
Design Cost: $155,202
Consultant: Bell & Spina 
Construction Cost: TBD
Contractor: TBD

Expected Start of Construction: May 2024
Expected Completion of Construction: October 2024

LATEST NEWS: Update current through 11/29/2022 --- This project is currently in design and has been deferred for construction until the Summer 2024, with bidding expected in the Fall 2023.  

top


Project 051010-00: Rehab Maytum/Reed/McEwen Plaza (SUCF PROJECT

Project Phase: Construction    
Consultant: Bell & Spina
Contractor: Savarino Companies 
Expected Completion of Construction: Spring 2023

LATEST NEWS: Update current through 11/29/2022-- In Construction - Contractors will need to return in Spring 2023 to complete the project. 

top


Project 051011-00: Rehab Exterior Reed Library (SUCF PROJECT

Project Phase: Construction    
Consultant: Bell & Spina
Contractor: Savarino Companies 
Expected Completion of Construction: October 2022

LATEST NEWS: Update current through 11/29/2022 -- In Construction - Nearing completion.

top

 


Project: 052201 - Mason Hall Temporary Cooling (SUCF PROJECT

Project Phase: Design Phase   
Consultant: Pathfinder
Contractor:  TBD

LATEST NEWS: Update current through 11/29/2022 -- This project is currently in design.

top


Project: 051022-00 Renovate Jewett Hall (SUCF PROJECT

Project Phase: Design Phase   
Consultant: Mitchell Giurgola Architects
Contractor:  TBD

LATEST NEWS: Update current through 11/29/2022 -- This project is currently in design.

top


Project: 051041 - Clean Energy Master Plan (SUCF PROJECT

Project Phase: Design Phase   
Consultant: M/E Engineering 
Contractor:  TBD

LATEST NEWS: Update current through 11/29/2022 -- This project is currently in design.

top


Project: 051043 - Replace Emergency Generators (SUCF PROJECT

Project Phase: Design Phase   
Consultant: Pathfinder
Contractor:  TBD

LATEST NEWS: Update current through 11/29/2022 -- This project is currently in design.