Facilities Planning Projects

Current Campus Projects:


Project Details:

Project D059IK - Residence Halls Condition Assessment 

Project Phase: Interview Phase  
Consultant: To Be Determined 

Expected Start of Services: Fall 2022 
Expected Completion of Services: December 2023

LATEST NEWS: Update current through 08/08/2022 -- The 3 highest ranked firms have been selected - interviews are scheduled for mid-September.  

RFQ Holders List 


Project M06512 - Summer 2022 Sidewalk Replacement & Fenton Hall Patio (FACILITIES SERVICES PROJECT)

Project Phase: CONSTRUCTION  
Consultant:  LaBella Associates 
Construction Cost: $97,600
Contractor: S. Tabone Construction  

Expected Start of Construction: July 2022 
Expected Completion of Construction: August 2022

LATEST NEWS: Update current through 08/08/2022 -- Construction Phase. 

 BID RESULTS        


Project 051024 - Lanford Rehab

Project Phase: CONSTRUCTION  
Design Cost:  $197,577.09
Consultant:  Flynn Battaglia Architects 
Construction Cost: $944,000
Contractor: Peak Construction 

Expected Start of Construction: Nov./Dec. 2021
Expected Completion of Construction: August 2022

LATEST NEWS: Update current through 08/08/2022 -- This project is in construction. 


Project: 051026 - Emergency Lockdown Door Hardware  

Project Phase: CONSTRUCTION
Design Cost: $88,610.85
Consultant: 3 Leafs Hardware Consultants  
Construction Cost: $475,000
Contractor: Huber Construction 

Expected Start of Construction: July 2022
Expected Completion of Construction: November 2022

LATEST NEWS: Update current through 08/08/2022 -- This project is in construction. 


Project: 051037 - Rehab Lanford Phase II - Exterior 

Project Phase: Design Phase    
Design Cost: $153,872.70
Consultant: Flynn Battaglia Architects 
Construction Cost: TBD
Contractor: TBD

Expected Start of Construction: TBD
Expected Completion of Construction: TBD 

LATEST NEWS: Update current through 08/08/2022 --- This project is currently in design.  

top


Project: 051038 - Replace Kirkland Plaza

Project Phase: Design Phase 
Design Cost: $196,548.14
Consultant: Bergmann
Construction Cost: TBD
Contractor: TBD

Expected Start of Construction: May 2023
Expected Completion of Construction: September 2023

LATEST NEWS: Update current through 08/08/2022 --- This project is currently in design. 

top


Project: 051039 - LoGrasso Hall Upgrade AHU & Ventilation System 

Project Phase: Design Phase
Design Cost: $267,428.11
Consultant: M/E Engineering 
Construction Cost: TBD
Contractor: TBD

Expected Start of Construction: May 2023
Expected Completion of Construction: August 2023

LATEST NEWS: Update current through 08/08/2022 --- This project is currently in design. 

top


Project: 051040 - Maytum Hall Roof Replacement 

Project Phase: Design Phase 
Design Cost: $155,202
Consultant: Bell & Spina 
Construction Cost: TBD
Contractor: TBD

Expected Start of Construction: May 2023
Expected Completion of Construction: October 2023

LATEST NEWS: Update current through 08/08/2022 --- This project is currently in design. 

top


Project: D059IE - Gregory Hall Exterior Masonry Repair

Project Phase: Design Phase 
Design Cost: $107,860
Consultant: Bell & Spina 
Construction Cost: TBD
Contractor: TBD

Expected Start of Construction: May 2023
Expected Completion of Construction: August 2023

LATEST NEWS: Update current through 08/08/2022 --- This project will be bidding for construction in the fall - Construction to now take place during the summer of 2023.  

top


Project 051010-00: Rehab Maytum/Reed/McEwen Plaza (SUCF PROJECT

Project Phase: Construction    
Consultant: Bell & Spina
Contractor: Savarino Companies 
Expected Completion of Construction: Summer 2022

LATEST NEWS: Update current through 08/08/2022-- In Construction

top


Project 051011-00: Rehab Exterior Reed Library (SUCF PROJECT

Project Phase: Construction    
Consultant: Bell & Spina
Contractor: Savarino Companies 
Expected Completion of Construction: September 2022

LATEST NEWS: Update current through 08/08/2022 -- In Construction

top


Project: 05X267 - Renovate Houghton Hall (SUCF PROJECT

PROJECT 05X267-07 - Houghton Math Fit-Out
Project Phase: Construction 
Consultant:  Mitchell Giurgola
Contractor: Peak Construction 

LATEST NEWS: Update current through -- 08/08/22 -- Substantially Complete - Punchlist. 

------------------------------------------------------------------------------------------------------------

PROJECT 05X267-00 - Houghton Hall 1st and 2nd Floor Fitout
Project Phase: Construction 
Consultant:  Mitchell Giurgola
Contractor:  Savarino Companies 

LATEST NEWS: Update current through 08/08/22 -- Substantially Complete - Punchlist. 

------------------------------------------------------------------------------------------------------------

PROJECT 05X267-06 - Houghton Animal Colony 
Project Phase: Construction 
Consultant:  Mitchell Giurgola
Contractor: Huber Construction 

LATEST NEWS: Update current through 08/08/22 -- Substantially Complete - Punchlist. 

top