Facilities Planning Projects
Current Campus Projects:
- 051038 - Replace Kirkland Plaza
- 051040 - Maytum Hall Lower Roof Replacement
- 051049 - Upgrade A/C & Humidity Controls - Mason Hall
- D059IK - Residence Halls Condition Assessment
- D059IE - Gregory Hall Exterior Masonry Repair
- 051024 - Lanford Rehab
- 051037 - Rehab Lanford Phase II - Exterior
- 051039 - LoGrasso Hall Upgrade AHU & Ventilation System
- State University Construction Fund (SUCF) PROJECTS
Project Details:
Project: 051038 - Replace Kirkland Plaza
Project Phase: Bid Review
Design Cost: $196,548.14
Consultant: Bergmann
Construction Cost: TBD
Contractor: TBD
Expected Start of Construction: May 2024
Expected Completion of Construction: September 2024
LATEST NEWS: Update current through 12/04/2023 --- 3 bids received on 12/1/23 - Bid Results
Notice to Bidders Current Plan Holders List
Project: 051040 - Maytum Hall Lower Roof Replacement
Project Phase: Bid Review
Design Cost: $155,202
Consultant: Bell & Spina
Construction Cost: TBD
Contractor: TBD
Expected Start of Construction: May 2024
Expected Completion of Construction: October 2024
LATEST NEWS: Update current through 11/29/2023 --- 2 Bids were received - Bid Results
Notice to Bidders Current Plan Holders List
Project 051049 - Upgrade Air Conditioning & Humidity Controls - Mason Hall
Project Phase: Closeout
Consultant: Pathfinder Engineers & Architects
Contractor: MLP Plumbing & Mechanical Construction Cost: $554,913.00
Expected Start of Services: May 2023
Expected Completion of Services: August 2023
LATEST NEWS: Update current through 11/14/2023 -- Construction is complete - In closeout phase.
Project D059IK - Residence Halls Condition Assessment
Project Phase: QAQC Phase
Consultant: Young + Wright Architectural
Contract Cost: $112,477.00
Expected Start of Services: Fall 2022
Expected Completion of Services: December 2023
LATEST NEWS: Update current through 11/14/2023 -- The Condition Assessment data was turned over to campus in October 2023.
Project: D059IE - Gregory Hall Exterior Masonry Repair
Project Phase: Construction Phase
Design Cost: $107,860
Consultant: Bell & Spina
Construction Cost: $634,316.50
Contractor: Upstate Restoration of NY
Expected Start of Construction: May 2023
Expected Completion of Construction: October 2023
LATEST NEWS: Update current through 11/14/2023 -- This project is nearing completion.
Project 051024 - Lanford Rehab
Project Phase: Punch list / Closeout
Design Cost: $197,577
Consultant: Flynn Battaglia Architects
Construction Cost: $1,105,162.73
Contractor: Peak Construction
Expected Completion of Construction: June 2023
LATEST NEWS: Update current through 11/14/2023 -- This project is in the closeout phase - Waiting on credit items from contractor.
Project: 051037 - Rehab Lanford Phase II - Exterior
Project Phase: Design Manual Phase
Design Cost: $153,872.70
Consultant: Flynn Battaglia Architects
Construction Cost: TBD
Contractor: TBD
Expected Start of Construction: TBD
Expected Completion of Construction: TBD
LATEST NEWS: Update current through 11/14/2023 --- This project is currently in the design manual phase.
Project: 051039 - LoGrasso Hall Upgrade AHU & Ventilation System
Project Phase: Closeout
Design Cost: $267,428.11
Consultant: M/E Engineering
Construction Cost: $2,214,948.00
Contractor: John W. Danforth Company
Expected Start of Construction: May 2023
Expected Completion of Construction: September 2023
LATEST NEWS: Update current through 11/14/2023 -- Construction is complete - In closeout phase.
Project 051010-00: Rehab Maytum/Reed/McEwen Plaza (SUCF PROJECT)
Project Phase: On Hold
Consultant: Bell & Spina
Contractor: Savarino Companies
Expected Completion of Construction: Summer 2023
LATEST NEWS: Update current through 11/14/2023 -- Project is on hold due to contractor filing bankruptcy.
Project: 051022-00 Renovate Jewett Hall (SUCF PROJECT)
Project Phase: Design Manual Phase
Consultant: Mitchell Giurgola Architects
LATEST NEWS: Update current through 11/14/2023 -- This project is currently in the design manual phase.
Project: 051041 - Clean Energy Master Plan (SUCF PROJECT)
Project Phase: Report Review
Consultant: M/E Engineering
LATEST NEWS: Update current through 11/14/2023 -- M/E Engineering has submitted their draft master plan report to SUCF and the campus for review.
Project: 051042 - Replace Turf Field & Track (SUCF PROJECT)
Project Phase: Design Phase
Consultant: PHZ Architects, PLLC
LATEST NEWS: Update current through 11/14/2023 --Artificial Turf Field (Phase I) - In pre-bid document phase, with construction scheduled for the spring 2024; Track & Field (Phase II) - In Design Manual phase.
Project: 051043 - Replace Emergency Generators (SUCF PROJECT)
Project Phase: Construction Contract Phase
Consultant: Pathfinder Engineers
Contractor: Frey Electric
LATEST NEWS: Update current through 11/14/2023 -- This project is currently in the construction contract phase with Frey Electric.
Project: 051044 - Replace Mechanical Equipment - Rockefeller Arts Center (SUCF PROJECT)
Project Phase: Design
Consultant: M/E Engineering
LATEST NEWS: Update current through 11/14/2023 -- A design kick-off meeting was held on 10/4/23.
Project: 051045 - Rehab Interior Reed Library - Learning Common (SUCF PROJECT)
Project Phase: Concept / Schematic Design Phase
Consultant: Architectural Resources
LATEST NEWS: Update current through 11/14/2023 -- This project is currently in the concept / schematic design phase.
Project: 051047 - Mason Hall Siding (SUCF PROJECT)
Project Phase: Out for Bid
Consultant: Holt Architects
LATEST NEWS: Update current through 11/14/2023 -- No bids were received.
Project: 051048 - Mason Hall Renovations (SUCF PROJECT)
Project Phase: Design Phase
Consultant: Architectural Resources
LATEST NEWS: Update current through 11/14/2023 -- A design kick-off meeting was held on October 17th.